Aeration System Trial - September 8
The Municipality will begin a trial of the lagoon aeration system on September 8, 2026, with both blowers operating simultaneously.
The goal is to increase dissolved oxygen (DO) in the aeration cell and improve treatment conditions, which is expected to help reduce odour impacts. Current DO levels are approximately 0.20 mg/L, with a target of 1.5–2.0 mg/L or greater.
The trial is expected to run for 14–21 days. Staff will monitor DO levels, treatment performance, air quality and odour conditions to determine whether the system is achieving the desired results.
Odours are likely to occur during the start-up and trial period.
Between September 9 and 10, staff also plan to apply sodium nitrate to the aeration cell to support the treatment process and help reduce odours. A second application may be used later in September if required.
Sludge Removal – October 5
The next phase of the project is scheduled to begin October 5, 2026. Bishop Water Technologies will remove accumulated sludge from one of the larger back ponds.
The work is expected to take approximately nine weeks, with contractors working six days per week.
Air quality during sludge removal will be monitored using equipment capable of measuring and recording volatile organic compounds (VOCs).
Whether the aeration blowers remain operating during sludge removal will depend on the results of the September aeration trial.