Step 1 – Pre- Consultation
Applicant consults with Municipal staff on the proposed project.
If a planning application is also required for the project the applicant will be directed to start a planning application with the County Planner.
Step 2 – Submission
Site Plan Control Application Requirements
Application Submissions must include:
- Site Plan Application- contact the Building and Planning Department to fill out a Site Plan Application
- Site Plan Checklist
- Supporting documentation and drawings
- Site Plan Fee and Deposit
Step 3 – Review of Submission
The site plan application is circulated to relevant commenting agencies, including but not limited to: municipal staff, municipal engineer, Saugeen Valley Conservation Authority, Bruce County Planner, MTO, service providers.
Step 4 – Address Comments
Any comments are sent to the applicant, so concerns can be addressed, and the application resubmitted with amendments or alterations.
Step 5 – Site Plan Agreement
Once all comments from commenting agencies have been addressed to the satisfaction of the Municipality a site plan agreement is drafted and sent to applicant for review.
Step 6 – Execution of Site Plan Agreement
Once the site plan agreement has been signed by the property owner or signing authority the agreement is taken to council with a staff report for consideration. Upon Council's approval a by-law is passed, and the agreement is signed and in effect. The Site Plan Agreement is then registered on title.